  • in reply to: Whole Day Appointments in Calendar Importer from Calendar Pack #9114
    mawim
    Participant

      Hello,

      thank you for your post and the email with the updated “Calendar Dates Importer 2.0.10”.

      Up to now it seems that nearly all issues are solved.

      Assigning categories to appointment is working again.
      And if the all day box is checked the appointments will be imported correctly.

      There is only one minor bug remaining. Importing an all day appointment works fine, but if you try to roll back this action by using the roll back function of the applet the appoint will not be removed. It will be converted to an appoint taking from midnight to 11 pm or so.

      Best regards
      Martin

      in reply to: Filing Assitant crashes with GW 2012 #9098
      mawim
      Participant

        Hello,

        thank you for your post and the email with the updated “Calendar Dates Importer 2.0.10”.

        Up to now it seems that nearly all issues are solved.

        Assigning categories to appointment is working again.
        And if the all day box is checked the appointments will be imported correctly.

        There is only one minor bug remaining. Importing an all day appointment works fine, but if you try to roll back this action by using the roll back function of the applet the appoint will not be removed. It will be converted to an appoint taking from midnight to 11 pm or so.

        Best regards
        Martin

        in reply to: Filing Assitant crashes with GW 2012 #9103
        mawim
        Participant

          Hello,

          indeed with GW2012SP1 most of the problems seem to be solved. With GW2012 w/o SP1 I still can reproduce all the crashes I encountered before.

          One issue is remaining. With Calendar Dates Importer (V. 2.0.9) if I checked the box “All day (24hours)” in the Day definition dialog I’d expect the items to be imported as an all day appointment an not as an appointment taking from 00:00 to 23:59.

          But the upgrade seems to cause a new bug. Also with Calendar Dates Importer it is not possible any more to assign a category to the impoted items.

          So finally the most importand issues are solved, but there is still some work to be done.

          My configuration:
          GW2012SP1 12.0.0 Bulid 101769 (EN DE)
          Windows 7 Professional (DE)
          Formative Runtime 2.6.0.0

          With best regards
          Martin

          mawim
          Participant

            Hello,

            I think, we misunderstood a little bit.

            Since GroupWise 7 Novell introduced all day events, shown in the calendar above normal appointments.

            Activating the “all day” check-box I’d expect appointments were imported into this part of the calendar. Up to now I could not manage to do so neither with GW7, GM8 nor with GW2012.

            With best regards
            Martin

            in reply to: Filing Assitant crashes with GW 2012 #9104
            mawim
            Participant

              Hello,

              I sent the request information to the email address mentioned.

              Latestly I found another issue where Formative crashes with GW2012.

              In “Import dates into your calendar” from the Calendar Pack nearly everything works fine, one problem is that using roll-back also leads to a crashing GW-client.

              Best